Numerical Simulation Study on Construction Effect of Top-Down Construction Method of Suspended Diaphragm Wall for Deep and Large Foundation Pit in Complex Stratum

Table 6

Summary of the corresponding position of the maximum subsidence of the surface.

Working procedureExternal surface of foundation pit (west)External surface of foundation pit (east)
Maximum settlement (mm)Distance from foundation pit edge (m)Maximum settlement (mm)Distance from foundation pit edge (m)

The first excavation (−2.000 m)−0.45910.00−0.47610.00
The third excavation (−13.400 m)−4.38515.00-4.39315.00
The fifth excavation (−24.550 m)−11.51120.00−11.51120.00
The seventh excavation (−34.145 m)−14.62120.00−14.52620.00
The tenth excavation (−51.630 m)−18.41915.00−17.77815.00