Risk Assessment of EPB Shield Construction Based on the Nonlinear FAHP Method
Table 3
Coupling matrix of EPB shield construction risk identification.
| Scale | Definition | Explanation |
| 0.5 | Equally important | The two factors are equally important. | 0.6 | Slightly more important | One factor is slightly more important than the other. | 0.7 | Obviously important | One factor is clearly important than the other. | 0.8 | Much more important | One factor is much more important than the other. | 0.9 | Extremely important | One factor is extremely important than the other. | 0.1, 0.2, 0.3, 0.4 | Converse comparison | If factor is compared with factor to get judgment , then factor is compared with factor to get judgment |
|
|