Research Article
Quality Risk Evaluation of Urban Rail Transit Construction Based on AHP–FCE Method
Table 4
Evaluation model indicator weights.
| C | Weight | λmax | C.I. | C.R. | Does it meet the test? | Combined weights | Sorting | B1 | B2 | B3 | B4 | B5 | 0.114 | 0.070 | 0.486 | 0.043 | 0.287 |
| Technical level of construction personnel C11 | 0.564 | | | | | 4.117 | 0.039 | 0.043 | Yes | 0.064 | 5 | Specification of construction personnel C12 | 0.263 | | | | | 0.030 | 10 | Management level of managers C13 | 0.055 | | | | | 0.006 | 17 | Safety awareness for construction workers C14 | 0.118 | | | | | 0.013 | 15 |
| Performance of machinery and equipment C21 | | 0.535 | | | | 4.147 | 0.049 | 0.054 | Yes | 0.038 | 7 | Maintenance of machinery and equipment C22 | | 0.130 | | | | 0.009 | 16 | Failure rate of machinery and equipment C23 | | 0.060 | | | | 0.004 | 19 | Level of monitoring of equipment C24 | | 0.275 | | | | 0.019 | 12 |
| Quality of materials on construction sites C31 | | | 0.498 | | | 4.034 | 0.011 | 0.013 | Yes | 0.242 | 1 | Availability of construction materials C32 | | | 0.121 | | | 0.059 | 6 | Stockpiling of construction materials C33 | | | 0.068 | | | 0.033 | 8 | Waterproofing of construction materials C34 | | | 0.313 | | | 0.152 | 2 |
| Soundness of programing C41 | | | | 0.482 | | 4.121 | 0.040 | 0.045 | Yes | 0.021 | 11 | Feasibility of construction handover C42 | | | | 0.057 | | 0.002 | 20 | Stability of formwork supports C43 | | | | 0.341 | | 0.015 | 14 | Production of construction site samples C44 | | | | 0.120 | | 0.005 | 18 |
| Geology of the construction site C51 | | | | | 0.515 | 4.037 | 0.012 | 0.014 | Yes | 0.148 | 3 | Buildings around the construction site C52 | | | | | 0.067 | 0.019 | 13 | Undercutting of municipal pipelines C53 | | | | | 0.112 | 0.032 | 9 | Environment of the construction site C54 | | | | | 0.306 | 0.088 | 4 |
|
|