Research Article

Quality Risk Evaluation of Urban Rail Transit Construction Based on AHP–FCE Method

Table 4

Evaluation model indicator weights.

CWeightλmaxC.I.C.R.Does it meet the test?Combined weightsSorting
B1B2B3B4B5
0.1140.0700.4860.0430.287

Technical level of construction personnel C110.5644.1170.0390.043Yes0.0645
Specification of construction personnel C120.2630.03010
Management level of managers C130.0550.00617
Safety awareness for construction workers C140.1180.01315

Performance of machinery and equipment C210.5354.1470.0490.054Yes0.0387
Maintenance of machinery and equipment C220.1300.00916
Failure rate of machinery and equipment C230.0600.00419
Level of monitoring of equipment C240.2750.01912

Quality of materials on construction sites C310.4984.0340.0110.013Yes0.2421
Availability of construction materials C320.1210.0596
Stockpiling of construction materials C330.0680.0338
Waterproofing of construction materials C340.3130.1522

Soundness of programing C410.4824.1210.0400.045Yes0.02111
Feasibility of construction handover C420.0570.00220
Stability of formwork supports C430.3410.01514
Production of construction site samples C440.1200.00518

Geology of the construction site C510.5154.0370.0120.014Yes0.1483
Buildings around the construction site C520.0670.01913
Undercutting of municipal pipelines C530.1120.0329
Environment of the construction site C540.3060.0884