Seismic Response Analysis of Secondary Lining Polymer Grouting Debonding Repair for Tunnel Construction Based on Parameter Inversion

Table 1

Tunnel section displacement change comparison table.

Construction stageLower step application initial liningPalm surface advance 20 mPalm surface advance 40 mPouring of second lining
Real measurement (mm)Finite element model (mm)Real measurement (mm)Finite element model (mm)Real measurement (mm)Finite element model (mm)Real measurement (mm)Finite element model (mm)

Peripheral convergence (K83 + 020)2.62.34.74.56.56.37.37.2

Vault settlement (K83 + 020)2.82.55.25.57.57.69.49.5

Vault settlement (K83 + 040)3.335.45.67.77.88.78.8