Research Article

Quantifying Schedule Delay Risk in Construction Projects: A Data-Driven Approach with BIM and Probabilistic Reliability Analysis

Table 4

Statistical parameters of each work area.

 SegmentAverage building area (m2/floor)Working days (day/floor)#Floors
OptimisticMost likelyPessimistic

BasementA11631517232
B25191719252
C47482324272
D43612224262

AbovegroundA23261113149
B35851315176
C31981213154