Research Article
Quantifying Schedule Delay Risk in Construction Projects: A Data-Driven Approach with BIM and Probabilistic Reliability Analysis
Table 6
Schedule network failure evaluation (deadline = 168 days).
| Methods | Failure probability (%) | Variation coefficient | Running time (ms) |
| LUBE | 1.52 | — | 0.3 ± 0.5 | Triangular fuzzy CPM | 27.64 | — | 0.7 ± 0.5 | Direct MCS (baseline) | 1.83 | 2.46% | 2914.8 ± 49.2 | Subset simulation | 1.74 | 5.63% | 751.5 ± 32.7 | FORM | 1.57 | — | 0.7 ± 0.6 | SORM (ours) | 1.75 | — | 1.5 ± 0.7 |
|
|