Quantifying Schedule Delay Risk in Construction Projects: A Data-Driven Approach with BIM and Probabilistic Reliability Analysis

Table 6

Schedule network failure evaluation (deadline = 168 days).

MethodsFailure probability (%)Variation coefficientRunning time (ms)

LUBE1.520.3 ± 0.5
Triangular fuzzy CPM27.640.7 ± 0.5
Direct MCS  (baseline)1.832.46%2914.8 ± 49.2
Subset simulation1.745.63%751.5 ± 32.7
FORM1.570.7 ± 0.6
SORM (ours)1.751.5 ± 0.7