Quantifying Schedule Delay Risk in Construction Projects: A Data-Driven Approach with BIM and Probabilistic Reliability Analysis
Table 7
System indices in the case project.
| | Without system | With system |
| Graphical presentation | | |
| Ego-level | Degree centrality | 15.67 | 6.05 (−61.4%) | Average distance | 22.5 | 3.82 (−83.0%) |
| Network-level | Density | 10% | 11.82% (+18.2%) | Average degree | 8.11 | 2.57 (−68.3%) | Diameter | 26 | 10 (−61.5%) | Effective size | 7.67 | 8.2 (+6.9%) |
|
|