Causes and Impacts of Delays in Ethiopian Public Construction Projects (Case on Debre Markos University Construction Projects)
Table 10
Mitigation measures for delay of DMU construction projects.
| | No | Method of resolving/minimizing delay | RII | Rank | Important level |
| | 1 | Complete and accurate project feasibility study | 0.9644 | 1 | High | | 2 | Awarding bids to the right/experienced consultant and contractor | 0.9535 | 2 | High | | 3 | Avoid the discrepancy in the drawings | 0.8791 | 3 | High | | 4 | Accurate initial time estimate | 0.8791 | 3 | High | | 5 | Strong supervision as per a schedule | 0.8698 | 5 | High | | 6 | Accurate initial cost estimate | 0.8698 | 5 | High | | 7 | Use of appropriate construction method | 0.8698 | 5 | High | | 8 | Allocation of sufficient time and money during the design phase | 0.8698 | 5 | High | | 9 | Ensuring adequate and available sources of finance | 0.8651 | 9 | High | | 10 | Top management support | 0.8558 | 10 | High | | 11 | Frequent progress meeting | 0.8465 | 11 | High | | 12 | Acceleration of site clearance | 0.8465 | 11 | High | | 13 | Performs preconstruction planning of project tasks and resources needs | 0.7953 | 13 | High medium | | 14 | The fast decision of site possession or removal of obstructions | 0.7860 | 14 | High medium | | 15 | Paying the payment at the right time | 0.7488 | 15 | High medium | | 16 | Avoidance of unclear and incomplete contract documents | 0.7395 | 16 | High medium | | 17 | Competent client representative | 0.6140 | 17 | High medium |
|
|