Causes and Impacts of Delays in Ethiopian Public Construction Projects (Case on Debre Markos University Construction Projects)

Table 10

Mitigation measures for delay of DMU construction projects.

NoMethod of resolving/minimizing delayRIIRankImportant level

1Complete and accurate project feasibility study0.96441High
2Awarding bids to the right/experienced consultant and contractor0.95352High
3Avoid the discrepancy in the drawings0.87913High
4Accurate initial time estimate0.87913High
5Strong supervision as per a schedule0.86985High
6Accurate initial cost estimate0.86985High
7Use of appropriate construction method0.86985High
8Allocation of sufficient time and money during the design phase0.86985High
9Ensuring adequate and available sources of finance0.86519High
10Top management support0.855810High
11Frequent progress meeting0.846511High
12Acceleration of site clearance0.846511High
13Performs preconstruction planning of project tasks and resources needs0.795313High medium
14The fast decision of site possession or removal of obstructions0.786014High medium
15Paying the payment at the right time0.748815High medium
16Avoidance of unclear and incomplete contract documents0.739516High medium
17Competent client representative0.614017High medium