Causes and Impacts of Delays in Ethiopian Public Construction Projects (Case on Debre Markos University Construction Projects)
Table 3
Summary of cost of contractors’ damage in Debre Markos University’s construction projects.
| | No. | Project category | Reason of cost | Total delayed time in a month | Average monthly overhead amount in millions of dollars | Total contract amount in delayed projects in millions of dollars | The magnitude of overhead cost in millions of dollars | % from project contract cost |
| | 1 | Selected 10 completed projects (Table 2) | | 59.63 | 44,780.74 | 102.20 | 26,702.75 | 2.61 | | 2 | Selected 12 ongoing projects (Table 4) | Overhead cost (20%) | 120.8 | 44,780.74 | 1,177.56 | 54,095.13 | 0.46 |
|
|