Causes and Impacts of Delays in Ethiopian Public Construction Projects (Case on Debre Markos University Construction Projects)

Table 4

The magnitude of delay of Debre Markos University’s 12 ongoing projects.

No.Project nameContractor nameConsultant nameOriginal contract amount in millions dollarsOriginal contract timeTime elapsed delaysTotal delayed time in daysJustified timeTotal delayed time in %Work executed in %Remark

1Hotel and truism buildingSaf ConADSC54.205401360820605151.8565Overrun
2Entrepreneurship buildingSaf ConADSC32.493651197832647227.9468Overrun
3Health compass landscape worksBok ConADSC164.6157093536524063.0428Delayed
4Bure compass infrastructuresMir ConADSC120.413645441803449.4575Delayed
5Bure compass library buildingsBark EngADSC40.11540573336.1143Delayed
6Water wall to main compassWWWEADSC24.69150553403268.6768Overrun
7Main compass administration buildingF-Stone conADSC121.5260010504507568.47Overrun
8Main campus to Adiss Alemayehu roundabout walkwayMisker G.CADSC12.41365800435218119.1858.5Overrun
9Main campus digital libraryL-Shayn PLCADSC115.0299080835.10
10Main campus postgraduate buildingKTY ConADSC278.4073043520.2
11Main campus ICT buildingK-Fitir ConADSC198.2773042522.4
12Henhouse constructionM-End BCADSC15.3936547110629.0467.0Delayed
Total1,177.5263099151362457.44

Source: Debre Markos University Construction Project Office.