Causes and Impacts of Delays in Ethiopian Public Construction Projects (Case on Debre Markos University Construction Projects)
Table 4
The magnitude of delay of Debre Markos University’s 12 ongoing projects.
| | No. | Project name | Contractor name | Consultant name | Original contract amount in millions dollars | Original contract time | Time elapsed delays | Total delayed time in days | Justified time | Total delayed time in % | Work executed in % | Remark |
| | 1 | Hotel and truism building | Saf Con | ADSC | 54.20 | 540 | 1360 | 820 | 605 | 151.85 | 65 | Overrun | | 2 | Entrepreneurship building | Saf Con | ADSC | 32.49 | 365 | 1197 | 832 | 647 | 227.94 | 68 | Overrun | | 3 | Health compass landscape works | Bok Con | ADSC | 164.61 | 570 | 935 | 365 | 240 | 63.04 | 28 | Delayed | | 4 | Bure compass infrastructures | Mir Con | ADSC | 120.41 | 364 | 544 | 180 | 34 | 49.45 | 75 | Delayed | | 5 | Bure compass library buildings | Bark Eng | ADSC | 40.11 | 540 | 573 | 33 | | 6.11 | 43 | Delayed | | 6 | Water wall to main compass | WWWE | ADSC | 24.69 | 150 | 553 | 403 | | 268.67 | 68 | Overrun | | 7 | Main compass administration building | F-Stone con | ADSC | 121.52 | 600 | 1050 | 450 | | 75 | 68.47 | Overrun | | 8 | Main campus to Adiss Alemayehu roundabout walkway | Misker G.C | ADSC | 12.41 | 365 | 800 | 435 | 218 | 119.18 | 58.5 | Overrun | | 9 | Main campus digital library | L-Shayn PLC | ADSC | 115.02 | 990 | 808 | — | | | 35.10 | | | 10 | Main campus postgraduate building | KTY Con | ADSC | 278.40 | 730 | 435 | | | | 20.2 | | | 11 | Main campus ICT building | K-Fitir Con | ADSC | 198.27 | 730 | 425 | | | | 22.4 | | | 12 | Henhouse construction | M-End BC | ADSC | 15.39 | 365 | 471 | 106 | — | 29.04 | 67.0 | Delayed | | Total | | | | 1,177.52 | 6309 | 9151 | 3624 | | 57.44 | | |
|
|
Source: Debre Markos University Construction Project Office.
|