Causes and Impacts of Delays in Ethiopian Public Construction Projects (Case on Debre Markos University Construction Projects)
Table 5
Cost of client’s damage in Debre Markos University’s project.
| | No | Project category | Original contract amount in millions dollar | Original contract time | Elapsed time | Delayed time in the day | Delayed time in the month | Monthly consulting fee in millions of dollars | Total consulting fee in the delayed time | % from project contract cost |