Causes and Impacts of Delays in Ethiopian Public Construction Projects (Case on Debre Markos University Construction Projects)

Table 5

Cost of client’s damage in Debre Markos University’s project.

NoProject categoryOriginal contract amount in millions dollarOriginal contract timeElapsed timeDelayed time in the dayDelayed time in the monthMonthly consulting fee in millions of dollarsTotal consulting fee in the delayed time% from project contract cost

1Selected 10 completed projects (Table 2)102.2020253819178959.63100,069.75.975.84
2Selected 12 ongoing projects (Table 4)1,177.18630991513624120.812.091.03
Sum1,279.408334129705413180.4318.066.87