Causes and Impacts of Delays in Ethiopian Public Construction Projects (Case on Debre Markos University Construction Projects)
Table 6
Questionnaire response rate.
| | Representing organizations | Questionnaire distributed | Questionnaire returned | % of return vs distribution |
| | Client (project owner) | 7 | 6 | 85.71 | | Consultant (engineer) | 18 | 15 | 83.33 | | Contractor | 25 | 22 | 88.00 |
|
|