Causes and Impacts of Delays in Ethiopian Public Construction Projects (Case on Debre Markos University Construction Projects)

Table 7

Respondents’ general opinion on their current project’s state.

NoScenariosRespondents’ responses in %
YesNo

1Do you think time overrun is a problem for DMU’s construction projects?87.412.6
3Do you think cost overrun is a problem for DMU’s construction projects?81.318.7
4Taking your current project into consideration, is the performance significantly behind schedule?67.432.6
5Did you conduct a complete and accurate project feasibility study before you start your work?65.134.9