Research Article

Causes and Impacts of Delays in Ethiopian Public Construction Projects (Case on Debre Markos University Construction Projects)

Table 8

Index of importance for the most essential factors in total outcomes.

NoCauses of project delayRIIRankFactors related

1Inaccurate time estimate0.97881Consultant
2Force majeure0.98842External
3Lowest bid procurement policy0.98473External
4Construction material market instability0.97534External
5Frequent design changes0.93455Consultant
6Delay in performing testing and inspection0.92656Consultant
7Failure to give written instruction0.927Consultant
8Late in reviewing and approving design document0.91218Consultant
9Financial capacity of the contractors0.9079Contractors
10Insufficient number of staff0.902310Client
11Slow decision making0.888411Client
12Information delays0.888412Client
13Change order0.885313Client
14Poor economic conditions0.881414External
15Preparing incomplete/undetailed BOQ0.879115Consultant
16Changes of mind during construction0.877616Client
17Shortage of construction material0.872117External
18Delay in approving a major change in the scope of work0.869818Consultant
19Inaccurate cost estimate0.869819Consultant
20Poor briefing of the document (specification, BOQ)0.860520Consultant
21Late delivery of materials0.860521Contractors
22Law-balling/low costing0.827922Contractors
23Inadequate preparation of tender and contract documents0.823323Consultant
24Poor coordination and communication with other parties0.82124Contractors
25Suspension of work upon the engineer’s instruction0.80325Contractors
26Late approval of payment0.826Consultant