Research Article

Causes, Effects, and Mitigation Measures of Time and Cost Overruns in Water Supply Projects: Case of Tigrai Region, Northern Ethiopia

Table 4

Top ten causes of time overrun ranked by respondents.

NosCauses of time overrunClient’s viewContractors’ viewConsultants’ viewOverall view
RIIRankRIIRankRIIRankRIIRank

1Design errors and changes99.95112.62121.01109.21
2Lack of consistency between bill of quantities and drawings97.96114.21120.92109.12
3Change order105.02107.63115.53108.23
4Shortage of construction materials and electromechanical equipment in local market101.0476.310107.3593.64
5Delays in material import (pipes, fittings, etc.)93.7787.8497.5892.15
6Ineffective planning and scheduling of projects by contractor107.4170.11590.01088.26
7Slow decision-making87.8980.96102.5687.97
8Contractor’s financial difficulties104.7377.7868.02086.08
9Poor contract management of the owner/consultant86.41069.116110.3483.79
10Delay in progress payments90.3882.0570.01782.810