Research Article
Causes, Effects, and Mitigation Measures of Time and Cost Overruns in Water Supply Projects: Case of Tigrai Region, Northern Ethiopia
Table 5
Top ten causes of cost overrun ranked by respondents.
| Nos | Causes of cost overrun | Clients’ view | Contractors’ view | Consultants’ view | Overall view | RII | Rank | RII | Rank | RII | Rank | RII | Rank |
| 1 | Design errors and changes | 89.7 | 1 | 90.9 | 1 | 89.7 | 2 | 90.3 | 1 | 2 | Lack of consistency between bill of quantities and drawings | 85.6 | 2 | 90.0 | 2 | 95.0 | 1 | 89.8 | 2 | 3 | Shortage of construction materials and electromechanical equipment in local market | 72.7 | 5 | 80.9 | 3 | 83.3 | 11 | 78.1 | 3 | 4 | Inconstancy of the price of materials | 72.2 | 6 | 80.8 | 4 | 76.6 | 15 | 76.5 | 4 | 5 | Change order | 75.6 | 3 | 71.3 | 10 | 87.8 | 5 | 76.3 | 5 | 6 | Delay in material delivery | 68.8 | 13 | 76.5 | 5 | 87.8 | 5 | 75.7 | 6 | 7 | Inadequate design supervision | 69.8 | 10 | 63.8 | 12 | 87.9 | 3 | 70.8 | 7 | 8 | Executive bureaucracy in the client’s organization | 66.0 | 15 | 72.0 | 9 | 76.6 | 15 | 70.6 | 8 | 9 | Poor communication b/n contractor and other parties | 73.1 | 4 | 60.9 | 15 | 85.3 | 8 | 70.5 | 9 | 10 | Client’s shortage of finance or delayed payments to contractors | 70.1 | 9 | 62.8 | 14 | 87.9 | 3 | 70.5 | 10 |
|
|