Causes, Effects, and Mitigation Measures of Time and Cost Overruns in Water Supply Projects: Case of Tigrai Region, Northern Ethiopia

Table 6

Linear regression for time overrun and model parameter estimates. Regression model: Log (time overrun) = β0 + β1 Der + β2 Lcs + β3 Cho + β4 Dmi.

Predictor variableParameter estimate

Constant, β01.658a
Design errors and changes (Der), (days), β10.005a
Inconsistency between bill of quantity and drawings (Lcs), (days), β2
Change order (Cho), (days), β30.06
Delays in material import (Dmi), (days), β40.004a
r2

Note: aParameter estimate significance (). Model fit significance ().