Causes, Effects, and Mitigation Measures of Time and Cost Overruns in Water Supply Projects: Case of Tigrai Region, Northern Ethiopia

Table 7

Linear regression for cost overrun and model parameter estimates regression model: cost overrun = β0 + β1 Der + β2 Lcs + β3 Inc + β4 Cho.

Predictor variableParameter estimate

Constant, β00.015
Design errors and change (Der), (millions), β11.054a
Inconsistency between bill of quantity and drawings (Lcs), (millions), β21.136a
Inconsistency of price of materials (Inc), (millions), β31.316a
Change order (Cho), (millions), β4
r2

Note: aParameter estimate significance (); model fit significance ().