Causes, Effects, and Mitigation Measures of Time and Cost Overruns in Water Supply Projects: Case of Tigrai Region, Northern Ethiopia

Table 8

Correlation among the respondents.

VariablesRespondentsClientContractorConsultant

Causes of time overrunClient
Contractor0.707∗∗
Consultant0.365∗∗0.568∗∗

Causes of cost overrunClient
Contractor0.857∗∗
Consultant0.738∗∗0.674∗∗

Effect of time overrunClient
Contractor0.853∗∗
Consultant0.630∗∗0.691∗∗

Effect of cost overrunClient
Contractor0.871∗∗
Consultant0.723∗∗0.802∗∗

Mitigation measures of time overrunClient
Contractor0.769∗∗
Consultant0.359∗∗0.675∗∗

Mitigation measures of cost overrunClient
Contractor0.764∗∗
Consultant0.443∗∗0.782∗∗

Note: Correlation is significant at the 0.05 level (2-tailed). ∗∗Correlation is significant at the 0.01 level (2-tailed).