Causes, Effects, and Mitigation Measures of Time and Cost Overruns in Water Supply Projects: Case of Tigrai Region, Northern Ethiopia
Table 8
Correlation among the respondents.
| Variables | Respondents | Client | Contractor | Consultant |
| Causes of time overrun | Client | — | | | Contractor | 0.707∗∗ | — | | Consultant | 0.365∗∗ | 0.568∗∗ | — |
| Causes of cost overrun | Client | — | | | Contractor | 0.857∗∗ | — | | Consultant | 0.738∗∗ | 0.674∗∗ | — |
| Effect of time overrun | Client | — | | | Contractor | 0.853∗∗ | — | | Consultant | 0.630∗∗ | 0.691∗∗ | — |
| Effect of cost overrun | Client | — | | | Contractor | 0.871∗∗ | — | | Consultant | 0.723∗∗ | 0.802∗∗ | — |
| Mitigation measures of time overrun | Client | — | | | Contractor | 0.769∗∗ | — | | Consultant | 0.359∗∗ | 0.675∗∗ | — |
| Mitigation measures of cost overrun | Client | — | | | Contractor | 0.764∗∗ | | | Consultant | 0.443∗∗ | 0.782∗∗ | |
|
|
Note: ∗Correlation is significant at the 0.05 level (2-tailed). ∗∗Correlation is significant at the 0.01 level (2-tailed).
|