Research Article

Causes, Effects, and Mitigation Measures of Time and Cost Overruns in Water Supply Projects: Case of Tigrai Region, Northern Ethiopia

Table 9

Findings of the case studies.

ProjectContract signed dateContract completion dateActual completionTime overruns (day)Initial contract amount (ETB)Actual cost (ETB)Cost overruns (ETB)Cost overrun, (%)

A07-08-0719-08-08Ongoing741135,202,397.4150,901,250.715,698,853.312
B09-07-0713-04-0821-10-0955317,556,161.119,401,165.91,845,004.810.5
C11-02-0925-07-0910-01-101655,403,696.56,645,094.21,241,397.723
D17-04-0722-01-0914-08-0914215,183,028.516,357,182.91,174,154.47.7
E20-11-0814-03-0907-12-08−975,549,151.55,715,598.9166,447.43
F27-10-0808-09-0920-08-09−1816,375,502.916,364,176.6−11,326.30
G22-04-0610-02-09Ongoing571136,892,950.5171,116,180.534,223,23025
H08-07-0709-04-08Ongoing87075,113,281.684,106,477.88,993,196.212
I12-04-0805-04-10Ongoing145125,850,628.3251,700,979.627,592,776.822
J22-10-0825-09-0903-11-09379,440,495.208,608,284.90−832,210.20−8.8
K05-08-0815-01-0915-02-09396,089,668.305,729,844.80−359823.4−6

Note: ETB = Ethiopian birr.