| Project | Contract signed date | Contract completion date | Actual completion | Time overruns (day) | Initial contract amount (ETB) | Actual cost (ETB) | Cost overruns (ETB) | Cost overrun, (%) |
| A | 07-08-07 | 19-08-08 | Ongoing | 741 | 135,202,397.4 | 150,901,250.7 | 15,698,853.3 | 12 | B | 09-07-07 | 13-04-08 | 21-10-09 | 553 | 17,556,161.1 | 19,401,165.9 | 1,845,004.8 | 10.5 | C | 11-02-09 | 25-07-09 | 10-01-10 | 165 | 5,403,696.5 | 6,645,094.2 | 1,241,397.7 | 23 | D | 17-04-07 | 22-01-09 | 14-08-09 | 142 | 15,183,028.5 | 16,357,182.9 | 1,174,154.4 | 7.7 | E | 20-11-08 | 14-03-09 | 07-12-08 | −97 | 5,549,151.5 | 5,715,598.9 | 166,447.4 | 3 | F | 27-10-08 | 08-09-09 | 20-08-09 | −18 | 16,375,502.9 | 16,364,176.6 | −11,326.3 | 0 | G | 22-04-06 | 10-02-09 | Ongoing | 571 | 136,892,950.5 | 171,116,180.5 | 34,223,230 | 25 | H | 08-07-07 | 09-04-08 | Ongoing | 870 | 75,113,281.6 | 84,106,477.8 | 8,993,196.2 | 12 | I | 12-04-08 | 05-04-10 | Ongoing | 145 | 125,850,628.3 | 251,700,979.6 | 27,592,776.8 | 22 | J | 22-10-08 | 25-09-09 | 03-11-09 | 37 | 9,440,495.20 | 8,608,284.90 | −832,210.20 | −8.8 | K | 05-08-08 | 15-01-09 | 15-02-09 | 39 | 6,089,668.30 | 5,729,844.80 | −359823.4 | −6 |
|
|