Large-Scale Construction Waste Mountain-Mounding Technology Based on the Project in Meibei Lake Scenic Area

Table 10

Summary of settlement values.

Work conditionsSettlement during construction (m)Settlement during consolidation (m)Total settlement during calculation (m)
ValuePercentage (%)ValuePercentage (%)

Construction period 12 months2.1280.30.5219.72.64
Construction period 18 months2.2584.90.4015.12.65
Construction period 24 months2.4189.90.2710.12.68