Large-Scale Construction Waste Mountain-Mounding Technology Based on the Project in Meibei Lake Scenic Area
Table 8
Summary of consolidation settlement calculations for Profile 3-3.
| | Profile 3-3 | End of construction | 12 Months after the end | 24 Months after the end |
| | Filling period of 12 months | | | | | Maximum settlement (m) | 2.12 | 2.48 | 2.64 | | Maximum horizontal displacement (m) | 0.44 | 0.428 | 0.420 | | Maximum superporous pressure (kPa) | 196.0 | 43.4 | 8.2 | | Degree of consolidation | 0.678 | 0.876 | 0.960 | | Filling period of 18 months | | | | | Maximum settlement (m) | 2.25 | 2.58 | 2.65 | | Maximum horizontal displacement (m) | 0.42 | 0.408 | 0.402 | | Maximum superporous pressure (kPa) | 128 | 34.6 | 6.1 | | Degree of consolidation | 0.768 | 0.931 | 0.978 | | Filling period of 24 months | | | | | Maximum settlement (m) | 2.41 | 2.64 | 2.68 | | Maximum horizontal displacement (m) | 0.40 | 0.392 | 0.391 | | Maximum superporous pressure (kPa) | 79.8 | 19.8 | 3.8 | | Degree of consolidation | 0.798 | 0.912 | 0.985 |
|
|