Large-Scale Construction Waste Mountain-Mounding Technology Based on the Project in Meibei Lake Scenic Area

Table 9

Summary of maximum superporous pressure and its occurrence.

Work conditionsMaximum overhole pressure during the whole processCalculation of end overhole pressure (kPa)
Maximum value (kPa)Time of occurrence

Construction period 12 months211.9T = 240 days, Mound height to elevation 432.5 m8.2
Construction period 18 months172.7T = 315 days, Mound height to elevation 430.0 m6.1
Construction period 24 months146.3T = 360 days, Mound height to elevation 427.5 m3.8