Large-Scale Construction Waste Mountain-Mounding Technology Based on the Project in Meibei Lake Scenic Area
Table 9
Summary of maximum superporous pressure and its occurrence.
| | Work conditions | Maximum overhole pressure during the whole process | Calculation of end overhole pressure (kPa) | | Maximum value (kPa) | Time of occurrence |
| | Construction period 12 months | 211.9 | T = 240 days, Mound height to elevation 432.5 m | 8.2 | | Construction period 18 months | 172.7 | T = 315 days, Mound height to elevation 430.0 m | 6.1 | | Construction period 24 months | 146.3 | T = 360 days, Mound height to elevation 427.5 m | 3.8 |
|
|