Research Article

Risk Factors for Time and Cost Overruns of Pipeline Projects in Saudi Arabia

Table 3

Questionnaire results.

Risk groupRisk codeRisk factorModeStandard deviation

DesignD1Defective designModerate0.71
D2Design change due to change ordersHigh0.70
D3Delay in drawing approvalHigh0.83

Health, safety and environmentHSE1Force majeure (earthquake, pandemics, etc.)Low1.05
HSE2Night Work (poor visibility, slip, and trip)Moderate0.75
HSE3Exposed existing pipelines during constructionModerate0.83
HSE4Inadequate site safety proceduresModerate0.81
HSE5Government permit approval delayHigh0.77
HSE6Geological factors like soil movement and landslidesModerate0.76
HSE7Accidents (human, vehicle, etc.)Moderate0.91

Security and socialSS1Terrorism and sabotageModerate1.00
SS2Reduction in the productive capacity of labor and machineryModerate0.77

SupplyS1Supplying invalid materialsModerate0.72
S2Materials monopoly by suppliersHigh0.70
S3Delays in materials and equipment supplyHigh0.73

FinancialF1Financial failure/bankruptcyHigh0.83
F2Inflation and Interest rate increaseHigh0.78
F3Increase in tax regulationHigh0.76
F4Increase of contractor’s project cost (cost overruns)Moderate0.71

ConstructionC1The discrepancy between implementation requirements and specificationsModerate0.76
C2Variation ordersHigh0.74
C3Poor pipeline material qualityHigh0.83
C4Corrosion of pipeline during its life cycle timeHigh0.81
C5Weakness in identifying and monitoring dangers.Moderate0.68
C6Operational errors (human error and equipment failure)High0.75
C7Unforeseen site circumstances (differing site conditions)Moderate0.64