|
| Risk group | Risk code | Risk factor | Mode | Standard deviation |
|
| Design | D1 | Defective design | Moderate | 0.71 |
| D2 | Design change due to change orders | High | 0.70 |
| D3 | Delay in drawing approval | High | 0.83 |
|
| Health, safety and environment | HSE1 | Force majeure (earthquake, pandemics, etc.) | Low | 1.05 |
| HSE2 | Night Work (poor visibility, slip, and trip) | Moderate | 0.75 |
| HSE3 | Exposed existing pipelines during construction | Moderate | 0.83 |
| HSE4 | Inadequate site safety procedures | Moderate | 0.81 |
| HSE5 | Government permit approval delay | High | 0.77 |
| HSE6 | Geological factors like soil movement and landslides | Moderate | 0.76 |
| HSE7 | Accidents (human, vehicle, etc.) | Moderate | 0.91 |
|
| Security and social | SS1 | Terrorism and sabotage | Moderate | 1.00 |
| SS2 | Reduction in the productive capacity of labor and machinery | Moderate | 0.77 |
|
| Supply | S1 | Supplying invalid materials | Moderate | 0.72 |
| S2 | Materials monopoly by suppliers | High | 0.70 |
| S3 | Delays in materials and equipment supply | High | 0.73 |
|
| Financial | F1 | Financial failure/bankruptcy | High | 0.83 |
| F2 | Inflation and Interest rate increase | High | 0.78 |
| F3 | Increase in tax regulation | High | 0.76 |
| F4 | Increase of contractor’s project cost (cost overruns) | Moderate | 0.71 |
|
| Construction | C1 | The discrepancy between implementation requirements and specifications | Moderate | 0.76 |
| C2 | Variation orders | High | 0.74 |
| C3 | Poor pipeline material quality | High | 0.83 |
| C4 | Corrosion of pipeline during its life cycle time | High | 0.81 |
| C5 | Weakness in identifying and monitoring dangers. | Moderate | 0.68 |
| C6 | Operational errors (human error and equipment failure) | High | 0.75 |
| C7 | Unforeseen site circumstances (differing site conditions) | Moderate | 0.64 |
|