Research Article
Construction Method and Process Optimization of Prestress Reverse Tensioning for Large-Span Bidirectional Suspension Steel Roof Structures
Table 5
Tensioning sequence of inhaul cables under each stag.
| Group | Stage | Order of cable tensioning |
| Group 1: Cables 6, 7, 8, 9 Group 2: Cables 4, 5, 10, 11 Group 3: Cables 2, 3, 12, 13 Group 4: Cables 1, 14 | Stage 1 | Group 1 ⟶ Group 2 ⟶ Group 3 ⟶ Group 4 | Stage 2 | Group 4 ⟶ Group 3 ⟶ Group 2 ⟶ Group 1 | Stage 3 | Group 1 ⟶ Group 2 ⟶ Group 3 ⟶ Group 4 |
|
|