Research Article

Performance of Diaphragm Walls during Ultra-Deep Excavations in Karst Areas: Field Monitoring Analysis

Table 4

Schedule of construction phases of Zone 4 and Zone 5.

ZonesDescriptionStart date (day from 2019/3/26)End date (day from 2019/3/26)

Zone 4Excavate to Level 1 (−5.0 m)2020/06/12 (Day 444)2020/07/02 (Day 464)
Construct 1st strut2020/07/07 (Day 469)2020/08/31 (Day 524)
Excavate to Level 2 (−10.0 m)2020/09/25 (Day 549)2020/10/30 (Day 584)
Construct 2nd strut2020/11/12 (Day 597)2021/02/06 (Day 683)
Excavate to Level 3 (−16.5 m)2021/02/20 (Day 697)2021/04/05 (Day 741)
Construct 3rd strut2021/04/13 (Day 749)2021/06/16 (Day 813)
Excavate to Level 4 (−20.45 m)2021/07/12 (Day 839)2021/07/21 (Day 848)
Construct 4th strut2021/07/24 (Day 851)2021/08/15 (Day 873)
Excavate to Level 5 (−26.45 m)2021/08/24 (Day 882)2021/09/16 (Day 905)
Construct 5th strut2021/09/21 (Day 910)2021/12/06 (Day 986)
Excavate to Level 6 (−34.68 m)2021/12/29 (Day 1,009)2022/05/08 (Day 1,139)

Zone 5Construct 1st strut2020/07/07 (Day 469)2020/07/15 (Day 477)
Excavate to Level 1 (−6.85 m)2020/07/22 (Day 484)2020/07/28 (Day 490)
Construct 2nd strut2020/08/04 (Day 497)2020/10/05 (Day 559)
Excavate to Level 2 (−13.15 m)2020/10/13 (Day 567)2020/10/27 (Day 581)
Construct 3rd strut2020/11/12 (Day 597)2020/12/04 (Day 619)
Excavate to Level 3 (−20.45 m)2020/12/14 (Day 629)2021/01/02 (Day 648)
Construct 4th strut2021/01/05 (Day 651)2021/02/03 (Day 680)
Excavate to Level 4 (−26.45 m)2021/02/12 (Day 689)2021/04/05 (Day 741)
Construct 5th strut2021/04/13 (Day 749)2021/05/09 (Day 775)
Excavate to Level 5 (−35.18 m)2021/05/17 (Day 783)2021/07/26 (Day 853)