Application of Data Mining Technology in Field Verification of Project Cost
Table 2
Summary of the completion of the plan.
| | Number | Plan | Actual | PPC (%) |
| | 1 | 846 | 928 | 91.14 | | 2 | 734 | 764 | 96.07 | | 3 | 860 | 928 | 92.65 | | 4 | 384 | 450 | 85.37 | | 5 | 349 | 464 | 75.20 | | 6 | 328 | 357 | 91.87 | | 7 | 342 | 307 | 111.39 | | 8 | 314 | 364 | 86.23 | | 9 | 405 | 486 | 83.41 | | 10 | 461 | 585 | 78.74 | | 11 | 540 | 518 | 104.21 | | 12 | 520 | 563 | 92.35 |
|
|