Research Article

Characterization of Vertical Response of Asphalt Trackbed Concrete in Railway Substructure to External Loads

Table 3

Material parameters of the ballastless railway track [10].

PartsGeometry (m)MaterialsElastic modulus (Pa)Poisson ratioDensity (kg/m3)Damping ratioRayleigh damping coefficients

RailUIC 60Steel2.06 × 10110.03078000.015
0.054
0.00094
Concrete slabWidth: 2.4
Thickness: 0.19
Cement concrete, C503.5 × 10100.16724500.030
0.105
0.016
CA layerWidth: 2.4
Thickness: 0.05
Cement, asphalt emulsion, and sand4 × 1080.16720500.035
0.09
0.011
Concrete baseWidth: 3
Thickness: 0.3
Cement concrete, C403.3 × 10100.16723000.030
0.16
0.00105
RoadbedWidth: 7.8
Thickness: 0.7
Crushed stone1.5 × 1080.25022000.045
0.13
0.011
SubgradeWidth: 11.25
Thickness: 2.3
A and B filler and improved soil0.6 × 1080.25020000.039
0.08
0.0925
GroundWidth: 45
Thickness: 40
A, B, and C filler and improved soil0.5 × 1080.33018000.035
0.091
0.0083