Research Article
Deformation Response Research of the Existing Subway Tunnel Impacted by Adjacent Foundation Pit Excavation
Table 5
Specific calculation steps.
| | Sequence | Construction sequence |
| | 1 | Generate the initial stress field | | 2 | Generate existing subway tunnel and buildings; reset displacement to zero | | 3 | Construct support piles | | 4 | Excavation to −0.5 m; slope support | | 5 | Excavation to −1.9 m; construct retaining wall | | 6 | Construction of the inner support system | | 7 | Precipitation to −11 m | | 8 | Excavation to −10.5 m |
|
|