Deformation Response Research of the Existing Subway Tunnel Impacted by Adjacent Foundation Pit Excavation

Table 5

Specific calculation steps.

SequenceConstruction sequence

1Generate the initial stress field
2Generate existing subway tunnel and buildings; reset displacement to zero
3Construct support piles
4Excavation to −0.5 m; slope support
5Excavation to −1.9 m; construct retaining wall
6Construction of the inner support system
7Precipitation to −11 m
8Excavation to −10.5 m