Important time points of the construction and operation phases.
| Day | Phase | Description |
| 0 | Construction | Construct the foundation | 35 | Backfill the foundation pit | 68 | Install the tower | 74 | Install the nacelle and rotor | 86 | Complete the installation |
| 103 | Operation | Start the operation | 117 | Operation case (hub wind speed = 12 m/s) | 200 | Operation case (hub wind speed = 14 m/s) | ... | Continue the operation |
|
|