Research Article

Mechanical Responses to Different Excavation Methods of Qichongcun Tunnel in Guiyang City, China

Table 3

Main calculation steps for the construction of the double-side guide pit method.

Calculation stepConstruction conditions

I.S.Clear the displacement
S1Excavate 1 m above the left guide pit
S2Excavate 1 m above the left guide pit; make the first step of the steel arch and initial lining
S3Excavate 1 m above the left guide pit; make the second step of the steel arch and initial lining
S4Excavate 1 m above the left guide pit; make the third step of the steel arch and initial lining
S5Excavate 1 m above the left guide pit; make the fourth step of the steel arch and initial lining
S6Excavate 1 m above and below the left guide pit; make the fifth step of the steel arch and initial lining
S7Excavate 1 m above and below the left guide pit; make the sixth step of the steel arch and initial lining
S8Excavate 1 m above and below the left guide pit; make the seventh step of the steel arch and initial lining
S9Excavate 1 m above and below the left guide pit; make the eighth step of the steel arch and initial lining
S10Excavate 1 m above and below the left guide pit; make the ninth step of the steel arch and initial lining
S11Excavate 1 m above the right guide pit; make the steel arch and initial lining of previous step
......
S16Excavate 1 m below the right guide pit; make the steel arch and initial lining of previous step
......
S21Excavate 1 m from middle and upper part of the tunnel; make the steel arch and initial lining of previous step
......
S26Excavate 1 m of the middle and lower part of the tunnel; make the steel arch and initial lining of previous step
......
S36Excavate inverted arch
S37Lay steel for inverted arch and pour inverted arch
S38Second lining