Mechanical Responses to Different Excavation Methods of Qichongcun Tunnel in Guiyang City, China

Table 5

Main calculation steps of the three-step method.

Calculation stepConstruction conditions

I.S.Clear the displacement
S1Excavate the first 1 m of the tunnel for anchor and lining
S2Excavate 1 m of the first step and the second step for the steel arch and lining
S3The first step, the second, and third steps are 1 m each for anchor the steel arch and lining
S4Excavate 1 m of the first, second, and third steps and make the steel arch and initial lining
S5Repeat the previous step
S6Repeat the previous step
S7Repeat the previous step
S8Repeat the previous step
......
S14Excavate inverted arch
S15Lay steel for inverted arch
S16Inverted arch
S17Second lining