[Retracted] Optimization Method of High-Speed Train Composite Material Workshop Planning and Scheduling
Table 1
Comparison of the effectiveness of three production planning operations.
| Scheduling times | Order delivery guarantee rate (%) | Total processing cycle | Bottleneck process load | Blade and body grinding 1 (%) | Surface grinding (%) | Machining center (%) |
| Pushing production schedule | 44 | 19 weeks | 75 | 70 | 64 | DBR scheduling | 61 | 16 weeks | 82 | 75 | 70 | Resource optimization scheduling | 67 | 13 weeks | 101 | 93 | 86 |
|
|