Cost Early-Warning Model System of Large-Scale Construction Project
Table 1
Evaluation index of earned value management.
Index
Calculation formula
Judging procedure
CV
CV = BCWP − ACWP
Measure the level of cost management. If CV < 0, it means that the project operation cost exceeds the expenditure; If CV ≥ 0, it means that the project operation cost saves expenses.
SV
SV = BCWP − BCWS
Measure the progress of the project. If SV < 0, it means that the project progress is delayed; If SV ≥ 0, it means that the project progress is ahead of schedule.
CPI
CPI = BCWP/ACWP
Measures the execution level of the project budget. If CPI < 1, it means that the cost exceeds the expenditure; If CPI ≥ 1, it means cost savings.
SPI
SPI = BCWP/BCWS
Measure the actual execution level of the project workload. If SPI < 1, the actual progress is insufficient; If SPI ≥ 1, it means that the actual progress is ahead.