Cost Early-Warning Model System of Large-Scale Construction Project

Table 1

Evaluation index of earned value management.

IndexCalculation formulaJudging procedure

CVCV = BCWP − ACWPMeasure the level of cost management.
If CV < 0, it means that the project operation cost exceeds the expenditure;
If CV ≥ 0, it means that the project operation cost saves expenses.

SVSV = BCWP − BCWSMeasure the progress of the project.
If SV < 0, it means that the project progress is delayed;
If SV ≥ 0, it means that the project progress is ahead of schedule.

CPICPI = BCWP/ACWPMeasures the execution level of the project budget.
If CPI < 1, it means that the cost exceeds the expenditure;
If CPI ≥ 1, it means cost savings.

SPISPI = BCWP/BCWSMeasure the actual execution level of the project workload.
If SPI < 1, the actual progress is insufficient;
If SPI ≥ 1, it means that the actual progress is ahead.