Analysis and Prediction of Subway Tunnel Surface Subsidence Based on Internet of Things Monitoring and BP Neural Network

Table 1

Comparison of several construction methods.

Comparison indicatorCut-and-cover method [16]Shield method [17]Shallow burial and underground excavation method [18]

GeologyVarious strata availableVarious strata availableWater-bearing formations require special treatment
PlaceOccupies more road areaTakes up less road areaTakes up less road area
Section changeGood adaptabilityPoor adaptabilityGood adaptability
Buried positionShallow burialNeed some depthShallow burial
Waterproof constructionEasierEasyDifficult
SubsidenceSmallerSmallerLarger
Traffic obstacleGreater impactLess affectedLess affected
Underground pipelineDemolition and protection requiredNo demolition and protection requiredNo demolition and protection required
Construction noiseBigSmallSmall
Surface demolitionBigSmallSmall
Water treatmentPrecipitation, dryingBlock and drop combinationBlock, drop, or block-drain combination
ScheduleAffected by demolition and relocation, and the total construction period is relatively fastThe preliminary project is complex and the total construction period is averageFast start and slow total construction period