| Importance sequence | Project risk factors | Probability average | Severity average | Probability average Severity average |
|
| 1 | Incorrect project orientation | 3.833 | 3.896 | 14.93 |
| 4 | Incorrect market demand forecasting | 3.958 | 3.646 | 14.43 |
| 34 | Thoughtless about inflation impact | 3.083 | 3.195 | 9.85 |
| 20 | Incorrect estimation about project investment | 3.25 | 3.229 | 10.49 |
| 29 | Incorrect estimation about return on investment (ROI) | 3.167 | 3.125 | 9.90 |
| 28 | Thoughtless about financing difficulty | 3.25 | 3.083 | 10.02 |
| 9 | Incorrect estimation about investment return | 3.417 | 3.5 | 11.96 |
| 26 | Thoughtless about financing difficulty | 3.167 | 3.229 | 10.23 |
| 30 | Government policy changes | 3.167 | 3.125 | 9.90 |
| 7 | Lack of external experts consultation | 3.688 | 3.396 | 12.52 |
| 31 | Thoughtless about project impact | 3.167 | 3.125 | 9.90 |
| 21 | Lack of field investigation and not adjusting measures to local conditions | 3.25 | 3.229 | 10.49 |
| 39 | Insufficient communication between designer and owner | 3.167 | 3.021 | 9.57 |
| 5 | Lack of innovation and applicability of design plan | 3.646 | 3.833 | 13.98 |
| 37 | Lack of designers’ full participation | 3.02 | 3.229 | 9.75 |
| 32 | Instability of safety equipment performance | 3.166 | 3.124 | 9.89 |
| 22 | Financing difficulty or rising costs | 3.25 | 3.229 | 10.49 |
| 33 | Improved environmental protection requirements on construction site | 3.164 | 3.123 | 9.87 |
| 23 | Materials and equipment supply not on time | 3.25 | 3.229 | 10.49 |
| 27 | Lack of experienced construction personnel | 3.25 | 3.146 | 10.22 |
| 16 | Inability or irresponsibility of contractors | 3.333 | 3.271 | 10.9 |
| 24 | Inability or irresponsibility of supervisors | 3.25 | 3.229 | 10.49 |
| 6 | Nontimely funding | 3.188 | 4.083 | 13.02 |
| 12 | Material price increase | 3.375 | 3.292 | 11.11 |
| 3 | Lack scientific construction process and method | 3.771 | 3.833 | 14.45 |
| 13 | Legal disputes of related subject | 3.374 | 3.291 | 11.10 |
| 17 | Worsening social order of project area | 3.333 | 3.271 | 10.90 |
| 8 | Opposition and obstruction to project construction | 3.125 | 3.958 | 12.37 |
| 2 | Lack good communication and cooperation among subjects | 3.917 | 3.75 | 14.69 |
| 11 | Bad weather or major natural disasters | 2.958 | 3.875 | 11.46 |
| 38 | Trial operation effect can not meet the design requirements | 3.083 | 3.125 | 9.63 |
| 25 | Instability of equipment performance | 3.25 | 3.229 | 10.49 |
| 14 | Speedy technology and equipment renewal | 3.373 | 3.290 | 11.09 |
| 18 | Technology and equipment maintenance is not timely | 3.333 | 3.271 | 10.90 |
| 35 | Rising operating costs | 3.083 | 3.188 | 9.83 |
| 36 | Sudden events | 2.979 | 3.292 | 9.81 |
| 10 | Major natural disasters | 2.958 | 3.917 | 11.59 |
| 15 | Lack of a clear accountability system | 3.371 | 3.289 | 11.07 |
| 19 | Lack of operation management or experiences | 3.333 | 3.271 | 10.90 |
|