The Portfolio Balanced Risk Index Model and Analysis of Examples of Large-Scale Infrastructure Project
Table 8
Three-dimensional evaluation data of single risk factor in the HZMB initial construction stage.
| | Stage | Sequence | Risk factors | Average value of probability | Average value of object severity | Average value of subject feeling |
| | Initial construction stage | 1 | Risk of being poorly designed (R11) | 2.17 | 3.65 | 3.42 | | 2 | Innovation risk (R12) | 2.52 | 3.48 | 3.07 | | 3 | Risk of nontimely funding (R21) | 2.08 | 4.16 | 3.66 | | 4 | The risk of rising costs (R22) | 3.21 | 3.23 | 2.77 | | 5 | The risk of regional system differences (R31) | 2.78 | 2.35 | 2.47 | | 6 | The public against risks (R32) | 1.56 | 3.72 | 3.98 | | 7 | Typhoon risk (R41) | 3.45 | 4.03 | 3.86 | | 8 | Earthquake risk (R42) | 1.06 | 4.75 | 4.67 | | 9 | Chloride salt corrosion risk (R43) | 2.72 | 3.25 | 3.09 | | 10 | Schedule control risk (R51) | 2.91 | 2.76 | 2.92 | | 11 | Quality management risk (R52) | 1.85 | 4.49 | 4.33 | | 12 | Safety management risk (R53) | 2.04 | 4.16 | 4.08 | | 13 | Legal conflict or blind area risk (R61) | 2.11 | 3.53 | 3.16 |
|
|