Robust Optimization for Integrated Construction Scheduling and Multiscale Resource Allocation
Table 3
Comparison of cost between multiscale and single-scale resource allocation strategy.
| Solution number | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | Avg. |
| Strategy 1: allocate permanent and temporary workers | 44.64 | 39.00 | 44.06 | 38.62 | 38.73 | 39.79 | 41.01 | 44.33 | 41.27 | Strategy 2: allocate permanent workers only | 47.34 | 40.33 | 45.86 | 40.40 | 40.57 | 40.95 | 42.45 | 46.01 | 42.99 | Strategy 3: allocate temporary workers only | 62.97 | 62.25 | 63.46 | 62.43 | 62.11 | 62.57 | 61.91 | 63.43 | 62.64 | Gap between strategy 1 and strategy 2 | 2.71 | 1.33 | 1.81 | 1.78 | 1.85 | 1.16 | 1.45 | 1.67 | 1.72 | Gap between strategy 1 and strategy 3 | 18.34 | 23.24 | 19.41 | 23.80 | 23.38 | 22.78 | 20.90 | 19.10 | 21.37 |
|
|