Research Article

Social Risk Assessment and Management for Major Construction Projects in China Based on Fuzzy Integrated Analysis

Table 2

Ranking of social risk factors based on the questionnaire results.

Social risk factorsPOMIIRLRankNormalized valuesSourcesStakeholders

Unfair compensation for housing demolition and land requisition5.065.445.2511.00[1, 3, 4, 18, 26, 28, 29]Government/residents/contractor/owner
Poor credibility of government5.134.945.0320.90[4, 6]Government/residents/owner/contractor/community
Forced demolition4.755.254.9930.89[4, 18]Government/residents/contractor
Engineering quality problems4.815.004.9140.85[4, 13, 18]Government/contractor/owner/supervisor
Violation of laws and rules4.634.944.7850.79[4, 18]Government/residents/contractor
Disturbance of local residents4.814.694.7560.78[6]Government/residents
Government’s improper administration4.694.814.7570.78[1, 3, 4, 11]Government/residents
Environment pollution (water, land, noise, etc.)5.064.444.7480.78[1, 3, 4, 6, 14, 28, 30]Government/contractor/residents/supervisor/community
Unreasonable relocation4.694.754.7290.77[1, 3, 4, 11]Residents/contractor
Security hidden danger4.504.754.62100.72[3, 4, 11, 18, 19, 26]Government/residents/contractor/ owner/supervisor
Negative attitudes of local residents towards project4.564.504.53110.68[1, 3, 4, 11]Government/residents
Lack of funds4.944.134.51120.67[3, 4, 11, 26]Government/owner/contractor
Lack of information on key stakeholders’ interests4.634.064.34130.60[3, 4, 11]Government/residents/contractor/ owner/supervisor
Variations in policies or compensation standards4.254.194.22140.54[1, 18]Supplier/contractor
Decision-maker moral4.194.134.16150.52[3, 4, 11]Government/contractor/owner/supervisor
Media dissemination4.134.134.13160.50Residents/media/public
Unemployment problem4.194.064.13170.50[3, 4, 26]Residents/contractor/supervisor
Decision-maker competence3.944.314.12180.50[1]Government/residents/contractor/owner/supervisor
Public opinion/rumor4.004.134.06190.47[4, 6, 18]Residents/contractor/community
Unreasonable project design3.943.943.94200.42[1, 4, 6]Design institute/contractor
Insufficient protection for vulnerable groups3.813.883.84210.38[1, 3, 4, 26]N/A
Cost overrun3.883.693.78220.35[1, 4, 11, 18, 19]Government/owner/contractor
Road occupancy/traffic disruption4.003.563.78230.35[1, 3, 4, 18]Residents/contractor/community
Improper drawing3.753.753.75240.34[1, 4, 6, 26]Design institute/contractor/owner
Enterprises losses caused by land acquisition3.813.693.75250.34[3, 4, 18]Government/ enterprises/residents
Unreasonable feasibility studies4.063.443.74260.33[1, 4, 17]Design institute
Conflict of construction projects3.693.693.69270.31[4, 6, 11, 18, 26]Contractor/owner
Error in construction site investigation3.693.693.69280.31[11, 18]Contractor/owner
Project schedule delays3.753.633.69290.31[1, 4, 11, 14]Government/contractor/owner
Lack of skill and experience of construction workers3.633.633.63300.28[1, 4, 6, 26]Government/residents/contractor/owner
Cultural conflicts3.503.753.62310.28[1, 3, 4, 17, 26]Contractor/designer
Financial crisis3.383.693.53320.24[4, 14]Government/contractor
Rising consumer prices2.883.813.31330.14[1, 18]Government/residents/contractor
Ineffective waste disposal3.383.133.25340.11[3, 4, 11, 18]Residents/contractor/supervisor
Uncertainties in weather and environment2.813.192.99350.00[1, 3, 4, 26]N/A