Research Article

An Assistance to Project Risk Management Based on Complex Systems Theory and Agile Project Management

Table 3

The 56-risk list with associated class, owner, and assessment.

IDRisk nameClassOwnerProbabilityGravityCriticality

1Safety studiesTechnical1111
2Liquidated damages on intermediate milestone and delay of Progress Payment ThresholdContractual27856
3Vehicle storage in another cityContractual19545
4Vandalism on-siteContractual3133
5Traction/braking function: behavior in degraded mode on slopeTechnical1326
6New local laws and regulationsContractual1133
7Traffic signaling, priority at intersectionsContractual46530
8Unclear interface with the client, for infrastructure equipmentContractual5122
9Delays due to client late decisionsContractual5919
10Travel time performanceTechnical4133
11Limited force majeure definitionContractual2144
12Operating certificate delayContractual29436
13Reliability and availability targetsTechnical4339
14Permissions and authorizationsContractual29218
15Insurance deductiblesFinancial6133
16Archeological findingsContractual29327
17Discrepancies client/operator/concessionaireContractual73515
18Civil Work delay and continuityContractual89436
19Responsibility of client on Civil Work delayContractual29218
20On board CCTV scopeTechnical9515
21Noise and vibration attenuationTechnical43618
22Potential risks of claim from Civil Work subcontractorContractual25525
23Harmonics levelTechnical5122
24Noncompliance contractual rolling stockTechnical1166
25Noncompliance technical specifications Rolling stockContractual13412
26Exchange risk on suppliersFinancial6133
27Track installation machine performanceClient/partner/subcontractor10326
28Tax risk on onshoreFinancial6122
29Additional poles over cost for tramway companyContractual59436
30Over cost due to security requirements for trainsTechnical45420
31Track insulationTechnical9111
32Delay for energizingProject management, construction site5326
33Fare collection requirementsContractual75315
34Construction safety interfacesTechnical3111
35Electromagnetic interferencesTechnical4122
36Exchange riskFinancial6122
37Risk of partial rejection of our request for EOT (Extension of Time)Contractual29763
38Interface rail/wheelTechnical4326
39Risk on certification of our equipmentCountry11122
40OCS installationProject management, construction site37535
41Banks stopping financing the projectContractual27321
42Costs of modifications not covered by EOT agreementContractual2144
43Return profit decreaseFinancial29872
44Extra trainsContractual4166
45Pedestrian zonesTechnical4122
46Train performanceTechnical1326
47Waiting time at stationsContractual4515
48Depot delayTechnical39218
49Error in the survey (topography)Technical4111
50Ticketing design delaysContractual7717
51Track installation delayTechnical37214
52Reengineering/redesignTechnical49218
53Slabs pouring delayTechnical3515
54Initial specifications of CW (Civil Work)Technical3515
55Available cash flow decreaseFinancial29763
56Rolling stock delivery delayTechnical1313