ID | Risk name | Class | Owner | Probability | Gravity | Criticality |
|
1 | Safety studies | Technical | 1 | 1 | 1 | 1 |
2 | Liquidated damages on intermediate milestone and delay of Progress Payment Threshold | Contractual | 2 | 7 | 8 | 56 |
3 | Vehicle storage in another city | Contractual | 1 | 9 | 5 | 45 |
4 | Vandalism on-site | Contractual | 3 | 1 | 3 | 3 |
5 | Traction/braking function: behavior in degraded mode on slope | Technical | 1 | 3 | 2 | 6 |
6 | New local laws and regulations | Contractual | 1 | 1 | 3 | 3 |
7 | Traffic signaling, priority at intersections | Contractual | 4 | 6 | 5 | 30 |
8 | Unclear interface with the client, for infrastructure equipment | Contractual | 5 | 1 | 2 | 2 |
9 | Delays due to client late decisions | Contractual | 5 | 9 | 1 | 9 |
10 | Travel time performance | Technical | 4 | 1 | 3 | 3 |
11 | Limited force majeure definition | Contractual | 2 | 1 | 4 | 4 |
12 | Operating certificate delay | Contractual | 2 | 9 | 4 | 36 |
13 | Reliability and availability targets | Technical | 4 | 3 | 3 | 9 |
14 | Permissions and authorizations | Contractual | 2 | 9 | 2 | 18 |
15 | Insurance deductibles | Financial | 6 | 1 | 3 | 3 |
16 | Archeological findings | Contractual | 2 | 9 | 3 | 27 |
17 | Discrepancies client/operator/concessionaire | Contractual | 7 | 3 | 5 | 15 |
18 | Civil Work delay and continuity | Contractual | 8 | 9 | 4 | 36 |
19 | Responsibility of client on Civil Work delay | Contractual | 2 | 9 | 2 | 18 |
20 | On board CCTV scope | Technical | 9 | 5 | 1 | 5 |
21 | Noise and vibration attenuation | Technical | 4 | 3 | 6 | 18 |
22 | Potential risks of claim from Civil Work subcontractor | Contractual | 2 | 5 | 5 | 25 |
23 | Harmonics level | Technical | 5 | 1 | 2 | 2 |
24 | Noncompliance contractual rolling stock | Technical | 1 | 1 | 6 | 6 |
25 | Noncompliance technical specifications Rolling stock | Contractual | 1 | 3 | 4 | 12 |
26 | Exchange risk on suppliers | Financial | 6 | 1 | 3 | 3 |
27 | Track installation machine performance | Client/partner/subcontractor | 10 | 3 | 2 | 6 |
28 | Tax risk on onshore | Financial | 6 | 1 | 2 | 2 |
29 | Additional poles over cost for tramway company | Contractual | 5 | 9 | 4 | 36 |
30 | Over cost due to security requirements for trains | Technical | 4 | 5 | 4 | 20 |
31 | Track insulation | Technical | 9 | 1 | 1 | 1 |
32 | Delay for energizing | Project management, construction site | 5 | 3 | 2 | 6 |
33 | Fare collection requirements | Contractual | 7 | 5 | 3 | 15 |
34 | Construction safety interfaces | Technical | 3 | 1 | 1 | 1 |
35 | Electromagnetic interferences | Technical | 4 | 1 | 2 | 2 |
36 | Exchange risk | Financial | 6 | 1 | 2 | 2 |
37 | Risk of partial rejection of our request for EOT (Extension of Time) | Contractual | 2 | 9 | 7 | 63 |
38 | Interface rail/wheel | Technical | 4 | 3 | 2 | 6 |
39 | Risk on certification of our equipment | Country | 11 | 1 | 2 | 2 |
40 | OCS installation | Project management, construction site | 3 | 7 | 5 | 35 |
41 | Banks stopping financing the project | Contractual | 2 | 7 | 3 | 21 |
42 | Costs of modifications not covered by EOT agreement | Contractual | 2 | 1 | 4 | 4 |
43 | Return profit decrease | Financial | 2 | 9 | 8 | 72 |
44 | Extra trains | Contractual | 4 | 1 | 6 | 6 |
45 | Pedestrian zones | Technical | 4 | 1 | 2 | 2 |
46 | Train performance | Technical | 1 | 3 | 2 | 6 |
47 | Waiting time at stations | Contractual | 4 | 5 | 1 | 5 |
48 | Depot delay | Technical | 3 | 9 | 2 | 18 |
49 | Error in the survey (topography) | Technical | 4 | 1 | 1 | 1 |
50 | Ticketing design delays | Contractual | 7 | 7 | 1 | 7 |
51 | Track installation delay | Technical | 3 | 7 | 2 | 14 |
52 | Reengineering/redesign | Technical | 4 | 9 | 2 | 18 |
53 | Slabs pouring delay | Technical | 3 | 5 | 1 | 5 |
54 | Initial specifications of CW (Civil Work) | Technical | 3 | 5 | 1 | 5 |
55 | Available cash flow decrease | Financial | 2 | 9 | 7 | 63 |
56 | Rolling stock delivery delay | Technical | 1 | 3 | 1 | 3 |
|