Risk Evaluation of Sewage Treatment PPPABS Projects Using Combination Weight Method and D-S Evidence Theory
Table 3
Final risk system of sewage treatment PPPABS projects.
| | First-level risk factors | Second-level risk factors | References |
| | A1: macrorisks | C1: interest risk | Farooquee [8] | | C2: law risk | Austin et al. [10] | | C3: political risk | Liu et al. [13] |
| | A2: basic asset risks | C4: quality risk | Liang [11] | | C5: unsold risk | Hou [12] | | C6: cash flow prediction deviation risk | Hou [12] | | C7: basic asset compliance risk | Experts |
| | A3: transaction structure risks | C8: bankruptcy isolation risk | Liu and Shao [14] | | C9: prepayment risk | Liu et al. [13] | | C10: SPV bankruptcy risk | Hou [12] |
| | A4: operational risks | C11: underwriting and issue risk | Lyons and Martin [15] | | C12: service providers risk | Hou [12] | | C13: trustee risk | Farooquee [8] |
| | A5: other risks | C14: government contract fulfillment risk | Liu et al. [13] | | C15: majeure risk | Experts | | C16: credit enhancement | Lu et al. [9] | | C17: credit rating risk | Hou [12] |
|
|