Metro construction safety risk factors.
| Classification | Code | Name |
| E | E1 | Bad weather | E2 | Unknown geological conditions | E3 | Underground pipe breaks |
| H | H1 | Lack of contingency plans | H2 | Violations by operatives | H3 | Inadvertent handling by operatives | H4 | Lack of safety precautions | H5 | Ineffective supervision | H6 | Unclear construction site markings | H7 | Inappropriate communication with other units | H8 | Negligent site management | H9 | Inaction by site managers | H10 | Inadequate qualification levels of operatives |
| MAC | MAC1 | Mechanical breakdown |
| MAT | MAT1 | Falling material from high places | MAT2 | Missing drawings | MAT3 | Insufficient awareness of material properties |
| T | T1 | Lack of a dedicated construction programme | T2 | Lack of detailed exploration information | T3 | Poor construction workmanship | T4 | Missing construction permits | T5 | Incorrect construction procedure |
|
|