Activities involved in a project scheduling network for a coal plant.

ActivityActivity nameDuration (months)

(a, b)Piling plan and detail drawing1
(b, c)Piling construction (including pile testing)1
(b, e)Foundation plan (and beam) layout drawing1
(c, d)Construction of reinforced concrete foundation1
(e, f)Steel structure detail drawing2
(f, )Procurement of steel structure2
(, j)Erection of steel structure1
(a, h)Procuring specifications of the static equipment1
(h, i)Procurement of static equipment5
(j, k)Installation of static equipment2