Intelligent Critical Path Computation Algorithm Utilising Ant Colony Optimisation for Complex Project Scheduling
Table 3
Activities involved in the critical path of a coal plant scheduling network.
| Activity | Activity name | Critical path (month) |
| (a, b) | Piling plan and detail drawing | 1 | (b, c) | Piling construction (including pile testing) | | (c, e) | Foundation plan (and beam) layout drawing | 1 | (c, d) | Construction of reinforced concrete foundation | | (e, f) | Steel structure detail drawing | 2 | (f, ) | Procurement of steel structure | 2 | (, j) | Erection of steel structure | 1 | (a, h) | Procuring specifications of the static equipment | | (h, i) | Procurement of static equipment | | (j, k) | Installation of static equipment | 2 | Total | | 9 |
|
|