Development of a Financing Optimization Framework Based on Risk Simulation in BOT Projects: A Case Study of the Waste-to-Energy Project
Table 11
Project implementation time and cost at 50%, 70%, and 90% confidence levels.
| Item | Initial estimate | Confidence level | 50% | 70% | 90% |
| Construction period time (days) | 1,095 | 1,450 | 1,490 | 1,540 | Construction period cost (billion tomans) | 510 | 582 | 592 | 606 | Operation period cost (billion tomans) | 1,700 | 1,819 | 2,213 | 2,949 | Total cost (billion tomans) | 2,210 | 2,400 | 2,795 | 3,526 |
|
|