Development of a Financing Optimization Framework Based on Risk Simulation in BOT Projects: A Case Study of the Waste-to-Energy Project

Table 3

Ranking the impact of risk occurrence.

ItemImpact (% of the change in objective)

ObjectiveVery lowLowModerateHighVery high
CostSmallLess than 10%10% to 20%20% to 40%More than 40%
TimeSmallLess than 5%5% to 10%10% to 20%More than 20%
OtherSmallLess than 10%10% to 20%20% to 50%More than 50%
Rank12345