Modeling and Solving the Flow-Shop Scheduling Problem with Sequence-Dependent Setup Times by Firefly Algorithm (Case Study: Automotive Industry)
Table 12
Sequence of job 1 operations.
| Job | Operation | Machine | Start time | Final time | Duration |
| 1 | 1 | 1 | 0 | 91.27 | 91.27 | 1 | 2 | 2 | 91.27 | 186.55 | 95.28 | 1 | 5 | 5 | 0 | 129.29 | 129.29 | 1 | 6 | 6 | 146.15 | 190.32 | 44.17 | 1 | 7 | 7 | 190.32 | 280.26 | 89.94 | 1 | 11 | 11 | 0 | 36.75 | 39.75 | 1 | 12 | 12 | 39.32 | 78.95 | 39.63 | 1 | 13 | 13 | 78.95 | 148.58 | 69.63 | 1 | 14 | 14 | 148.58 | 199.59 | 51.01 | 1 | 15 | 15 | 199.59 | 260.37 | 60.78 | 1 | 9 | 9 | 0 | 133.9 | 133.9 | 1 | 10 | 10 | 305.35 | 360.39 | 55.04 | 1 | 16 | 16 | 260.37 | 347.6 | 57.23 | 1 | 17 | 17 | 347.6 | 451.31 | 103.71 | 1 | 4 | 4 | 213.79 | 248.29 | 226.5 | 1 | 3 | 3 | 186.55 | 261.61 | 75.06 | 1 | 8 | 8 | 311.1 | 346.76 | 35.66 |
|
|