Modeling and Solving the Flow-Shop Scheduling Problem with Sequence-Dependent Setup Times by Firefly Algorithm (Case Study: Automotive Industry)

Table 12

Sequence of job 1 operations.

JobOperationMachineStart timeFinal timeDuration

111091.2791.27
12291.27186.5595.28
1550129.29129.29
166146.15190.3244.17
177190.32280.2689.94
11111036.7539.75
1121239.3278.9539.63
1131378.95148.5869.63
11414148.58199.5951.01
11515199.59260.3760.78
1990133.9133.9
11010305.35360.3955.04
11616260.37347.657.23
11717347.6451.31103.71
144213.79248.29226.5
133186.55261.6175.06
188311.1346.7635.66