Research Article

Modeling and Solving the Flow-Shop Scheduling Problem with Sequence-Dependent Setup Times by Firefly Algorithm (Case Study: Automotive Industry)

Table 14

Sequence of job 3 operations.

JobOperationMachineStart timeFinal timeDuration

35260104.19104.19
366104.19146.1541.96
311122.39160.0337.64
3224160.03272.24112.21
33250101.75101.75
344248.29287.439.11
3727146.15271.1612.01
388271.16311.139.94
3928311.1430.94119.84