Research Article

Modeling and Solving the Flow-Shop Scheduling Problem with Sequence-Dependent Setup Times by Firefly Algorithm (Case Study: Automotive Industry)

Table 15

Sequence of job 4 operations.

JobOperationMachineStart timeFinal timeDuration

41212039.3239.32
4133539.32153.92193.24
4229094.1794.17
433094.17144.8150.64
49330108.22108.22
41010254.96305.3550.39
41134305.35432.04126.69
444144.81183.838.99
4531183.8287.25103.45
466287.25333.646.35
4732090.9990.99
488346.76387.841.04
411186.58240.2753.69