Modeling and Solving the Flow-Shop Scheduling Problem with Sequence-Dependent Setup Times by Firefly Algorithm (Case Study: Automotive Industry)
Table 15
Sequence of job 4 operations.
| Job | Operation | Machine | Start time | Final time | Duration |
| 4 | 12 | 12 | 0 | 39.32 | 39.32 | 4 | 13 | 35 | 39.32 | 153.92 | 193.24 | 4 | 2 | 29 | 0 | 94.17 | 94.17 | 4 | 3 | 30 | 94.17 | 144.81 | 50.64 | 4 | 9 | 33 | 0 | 108.22 | 108.22 | 4 | 10 | 10 | 254.96 | 305.35 | 50.39 | 4 | 11 | 34 | 305.35 | 432.04 | 126.69 | 4 | 4 | 4 | 144.81 | 183.8 | 38.99 | 4 | 5 | 31 | 183.8 | 287.25 | 103.45 | 4 | 6 | 6 | 287.25 | 333.6 | 46.35 | 4 | 7 | 32 | 0 | 90.99 | 90.99 | 4 | 8 | 8 | 346.76 | 387.8 | 41.04 | 4 | 1 | 1 | 186.58 | 240.27 | 53.69 |
|
|