Research Article

Modeling and Solving the Flow-Shop Scheduling Problem with Sequence-Dependent Setup Times by Firefly Algorithm (Case Study: Automotive Industry)

Table 16

Sequence of job 4 operations.

JobOperationMachineStart timeFinal timeDuration

5538038.7138.71
56638.71100.4761.76
51191.27122.3931.12
5236052.7452.74
533752.74118.3865.64
544183.8213.7929.99
5739100.47196.3395.86
588196.33224.8428.51
5940224.84299.9675.12